Guides
9 min read· November 28, 2026

Types of pile foundations: how each is built, what it does to the soil, and how to choose

Types of pile foundations compared: driven piles, drilled shafts, CFA, helical and micropiles, with a worked example where a bored pile needs 8.6 m more length.


The main types of pile foundations are driven piles, drilled shafts (bored piles), auger cast (CFA) piles, helical piles and micropiles. They differ in more than construction method. The way a pile gets into the ground changes the soil around it, and that changes the capacity you can count on. This guide explains each type, then works one example: on the same site, under the same load, a bored pile needs 20.1 m where a driven pile of the same diameter needs 11.5 m.

When you need a pile foundation

Most structures sit on shallow footings, which spread the load over the soil near the surface. A pile foundation is what you use when that soil cannot do the job. A pile is a long, slender column that carries the load down past weak soil to ground that can take it. Engineers reach for piles when:

  • there is soft clay or loose fill near the surface,
  • the loads are too heavy for any reasonable footing,
  • the foundation has to resist uplift or sideways loads from wind, waves or earthquakes,
  • water could scour the soil away from under a footing.

How a pile carries load

Every pile carries load in two ways. The soil along its sides grips it: that is skin friction. The ground under its tip pushes back: that is end bearing. A pile that gets most of its capacity from the sides is a friction pile, and one that stands on rock or dense sand is an end bearing pile. Most real piles are a mix. The post on skin friction vs end bearing shows how to calculate both.

Both depend on the state of the soil right next to the pile: how tightly it is packed, and how hard it presses on the shaft. Installation changes exactly that, which is why the pile type belongs in the calculation and not only in the construction plan.

The five main types of pile

TypeHow it is builtWhat it does to the soilSuitsWatch for
Driven pileMade first (timber, precast concrete, steel H or pipe), then hammered inDisplaces it. In sand, the grains pack tighter around the pileTypical building and bridge loads, sand that densifiesNoise and vibration, boulders, a length fixed before driving
Drilled shaft (bored pile)A hole is drilled, a reinforcing cage lowered in, and the hole filled with concreteRemoves it. The ground around the hole relaxes, and the base can be loosenedVery heavy loads, large lateral loads, rock socketsQuality is made on site: caving, a dirty base, poor concrete
Auger cast (CFA) pileA hollow auger is screwed in, and concrete or grout is pumped through its stem as it comes outThe hole is never left openSoft or wet ground, quiet sitesDepends on rig control during withdrawal
Helical pileA steel shaft with screw plates, twisted in by a hydraulic motorLittle spoil and almost no vibrationLighter loads, tension, tight accessLower capacity per pile
MicropileA small drilled hole, usually under 300 mm, with a steel bar or casing grouted inDrills through boulders and rockUnderpinning, low headroomMany piles for a heavy load

Driven piles

A driven pile does not remove any soil. It pushes the soil aside. In sand, that packs the grains tighter and presses them against the pile, so both friction and end bearing go up. Driving also tests every pile: the number of hammer blows for the last few centimeters is a measure of resistance, on every pile on the site. The price is noise and vibration, which can rule out driving next to old buildings, and a length that is fixed before you start.

Drilled shafts

A drilled shaft, also called a bored pile, drilled pier or caisson, is the opposite. The soil is taken out, so the ground around the hole relaxes instead of tightening. Size for size, a drilled shaft in sand gets less from the soil than a driven pile. Its advantage is size: shafts can be two or three meters across and socketed into rock, so one shaft can replace a whole group of driven piles and carry large lateral loads. Because quality is made on site, shafts need careful inspection and integrity testing. PileCalc has a dedicated drilled shaft tool for large shafts and rock sockets.

Auger cast, helical and micropiles

Three more types fill the gaps. Auger cast piles are fast and quiet and suit soft or wet ground. Helical piles are light, carry tension as well as compression, and their installation torque is an indicator of capacity. Micropile rigs fit inside basements and under bridges, which makes micropiles the usual choice for underpinning existing structures.

Worked example: driven vs bored on the same site

InputValue
Layer 1Soft clay, 0 to 10 m, unit weight 18 kN/m³, undrained strength 25 kPa
Layer 2Sand, 10 to 40 m, unit weight 19 kN/m³, friction angle 35°
Water table2 m below the surface
Pile0.5 m diameter
Service load480 kN, with a factor of safety of 3
MethodNAVFAC DM-7.02

Start with the tip. End bearing in sand is the effective stress at the tip times a bearing capacity factor, Nq.

  1. The effective stress at the tip is about 100 kPa.
  2. For a driven pile at 35°, the NAVFAC manual gives Nq = 50. That is about 5,000 kPa, or about 1,000 kN on a 0.5 m tip.
  3. For a drilled pile, the same manual gives Nq = 25. The tip gives about 500 kN: same sand, same diameter, half the end bearing.
  4. The drilled pile has to find the missing 500 kN in friction. The sand gives about 58 kN per meter of pile, and 500 / 58 is nearly 9 m.

PileCalc's capacity vs length tool sweeps the length and reads off the first one that carries the load:

PileRequired length
Driven, 0.5 m11.5 m
Bored, 0.5 m20.1 m
Bored, 0.6 m12.2 m

The bored pile is 8.6 m longer, which matches the hand estimate. The third row shows there is usually more than one right answer: make the bored pile 10 cm wider and it needs about the same length as the driven one. The final choice then comes down to cost, time and the equipment available.

How to choose a pile type

  1. How big is the load? Light loads suit helical piles and micropiles. Typical building and bridge loads suit driven or auger cast piles. Very heavy loads and large lateral loads point to drilled shafts.
  2. What is the ground? Sand that gets denser when you drive into it favors driven piles. Rock near the surface, or boulders, favors drilling.
  3. What is next door? Driving is loud and shakes the ground. Near old buildings, hospitals or buried pipes, drilled or screwed piles are the usual choice.
  4. How much room is there? Low headroom and tight access call for micropiles or helical piles.
  5. How will you prove it? Driven piles are checked by the hammer, helical piles by torque, and drilled shafts by inspection and testing.

Four checks before you settle on a type

  • Know the ground first. The choice depends on what is down there and how deep the bearing layer is. A site investigation comes before everything else.
  • Match the method to the pile. A capacity worked out for a driven pile does not apply to a drilled one, even in the same soil.
  • Check more than capacity. Settlement, lateral loads and group effects can each govern the design.
  • A calculation is a prediction. On real projects it is confirmed by load tests, dynamic testing during driving, or integrity testing of drilled shafts.

Common questions

What are the main types of pile foundations?

Driven piles, drilled shafts (bored piles), auger cast or CFA piles, helical piles and micropiles. Driven piles displace the soil, drilled shafts replace it, and the other three cover soft ground, light loads and restricted access.

What is the difference between a driven pile and a bored pile?

A driven pile is made first and hammered in, which pushes the soil aside and, in sand, packs it tighter. A bored pile is cast in a drilled hole, so the soil is removed and the ground around the hole relaxes. For the same diameter in sand, design methods such as NAVFAC DM-7.02 give a bored pile less end bearing than a driven one.

Why does a bored pile need to be longer than a driven pile?

Because its end bearing is lower, the bored pile has to make up the difference in skin friction, and friction comes from length. In the worked example, halving the bearing capacity factor from 50 to 25 removes about 500 kN at the tip, which takes nearly 9 m of extra pile in sand to recover.

When is a drilled shaft better than driven piles?

When loads are very heavy or lateral loads are large, when rock is close enough to socket into, or when driving vibration is not acceptable. One large shaft can replace a group of driven piles.

How do engineers choose a pile type?

By the size of the load, the ground conditions, what is next to the site, the access and headroom, and how the capacity will be verified. Where more than one type works, cost, programme and locally available equipment decide.

Results are from the PileCalc engine for the inputs shown, rounded. This guide is educational and does not replace a site-specific design.

Keep reading

Guides
November 28, 2026

Drag load and the neutral plane: worked example

How to calculate drag load from negative skin friction: find the neutral plane, sum the friction above it, and run the three design checks. Worked example.

Read
Guides
November 28, 2026

Drilled shaft capacity: alpha and beta methods

Drilled shaft capacity by hand: the alpha method in clay, the beta method in sand, base resistance, and why the base carries so little at working load.

Read
Guides
November 28, 2026

Slope stability and the method of slices: worked example

Slope stability analysis from first principles: factor of safety, the method of slices, Bishop's simplified method and groundwater, with a worked example.

Read

See it for yourself

Run a laterally loaded pile in your browser — with the deflected shape, moment diagram, and every input explained.

Launch the app